Lithuania on collision course with EBRD over dismantling of Ignalina

Lithuania is following a two-track nuclear energy policy: it is decommissioning the closed-down Ignalina nuclear power plant and wants to build a new nuclear plant at Visaginas. Despite having recently selected GE-Hitachi as "strategic investor" for Visaginas, it is still far from certain whether this project will ever be realised. But the decommissioning project has also run into major problems. The Lithuanian government has come into sharp conflict with the European Bank for Reconstruction and Development (EBRD), which administers the decommissioning fund, about how to dismantle the plant. In addition, the project is facing a financing gap of €1.5 billion after 2014.

‘We are a nuclear community’, Lithuania's Federal Minister of Energy, Arvydas Sekmokas, recently proclaimed to a group of foreign journalists on a visit to Vilnius. According to Sekmokas, even the disaster at Fukushima did not significantly dent popular and parliamentarian support for the government’s plan to have a new nuclear power plant built by 2018. He cited several opinion polls showing that the Lithuanian people still mourn the loss of Ignalina, the Soviet-built nuclear plant that was shut down at the end of 2009 as a condition for Lithuania’s accession to the EU. Ignalina had been the country’s ticket to energy independence; since its closure Lithuania has become dependent on Russian gas and energy prices have gone up.

So is Sekmokas correct that the Lithuanian people still support nuclear power after Fukushima? According to a recent survey from the University of Technology in Kaunas, public support for a new nuclear power plant in Lithuania dropped from 60% to 10% after Fukushima. By contrast, the government claims that Fukushima led only to drop of support from 75% to 60%. However, the government seems to base this figure on the average of several opinion polls held since 2007. Between February and June 2011 the proportion of Lithuanians who “evaluated the use of nuclear energy positively” had according to these polls dropped from 58 to 44%. Very important in this regard is the attitude of the popular President Dalia Grybauskaite, Lithuania’s “Iron Lady”, who has expressed her support for the Visaginas project.

Unemployment rate

However the story of Visaginas may end (for more information see the box at the end of this article), at this very same time another nuclear drama is unfolding in Lithuania, which is getting a lot less attention. This revolves around the decomissioning of Ignalina.

When the second Ignalina reactor was taken off the grid at the end of 2009 (operations at the first one had been shut down at the end of 2004), from one day to the next Lithuania went from being a major

Very important in this regard is the attitude of the popular President Dalia Grybauskaite, Lithuania's "Iron Lady", who has expressed her support for the Visaginas project
power exporter (2009: +30.7%) to the largest energy importer in the EU (2010: -62.1%). Instead of the almost 5,000 employees that Ignalina had when it was running at full capacity, its staff numbers dwindled to about 2,000 today. The unemployment rate in the city of Visaginas (population 30,000), which was established by the Soviets for the sole purpose of operating the nuclear power plant, has risen threefold to more than 13%.

However, the Lithuanians have resigned themselves to their EU-imposed fate and have dedicated themselves to the decommissioning of Ignalina. At first glance, the decommissioning of nuclear power plants may seem much a less interesting affair than the building of new ones, but with growing numbers of nuclear power plants in Europe reaching the end of their lifetimes in the coming decades, decommissioning is bound to become an increasingly big issue. The European Commission estimates that approximately one third of the 145 power reactors currently operating in the European Union will need to be shut down by 2025. Experience gained so far (relatively few large-scale nuclear plants have as yet been dismantled) shows that the costs will be very large. For example, in France the decommissioning of the small 70 MW Brennilis Nuclear Power Plant cost €480 million. The current estimate by the United Kingdom's Nuclear Decommissioning Authority is that it will cost at least £70 billion to decommission the 19 existing nuclear sites in the UK.

Or, to put a more positive spin on it: decommissioning is bound to become a thriving business in the coming years. Indeed, this is exactly how the Lithuanian government looks at it. Lithuania’s Ministry of Energy views the dismantling of Ignalina as an opportunity to gain a wealth of expertise that other countries will find interesting. The Ignalina project is the first Soviet-style RBMK-reactor ever to be dismantled in the world (not counting the one at Chernobyl). It will serve as a model for reactors of the same type and for other types of reactors as well.

Dissatisfied

Unfortunately, the dismantling of Ignalina, which is supposed to return to “brown field” conditions in 2030, is not at all going smoothly. The first phase, which started at the end of 2004, is already three to

'We are dissatisfied with the bank and the agreement. It is insufficient in financial terms. And the EBRD waters down responsibility. It shows no responsibility'
four years behind schedule. Financing for the second long-term phase (2014-2029) has not been agreed upon yet. Representatives from the Lithuanian government made it clear to the foreign journalists in Vilnius that they are firmly at loggerheads with the European Bank for Reconstruction and Development (EBRD), which takes care of the funding of the project, and with the German company GNS (Gesellschaft für Nuklear Service GmbH), which is involved on the operational side.

The conflict seems to be essentially about who should be in charge of the process. It seems to have started when the conservative Homeland Union–Lithuanian Christian Democrats of Andrius Kubilius took power at the end of 2008. The new government felt that Lithuania was not treated as an equal partner. Ignalina’s Director of Corporate Affairs Osvaldas Èiukšys, an experienced diplomat, says that the agreements with the EBRD were appropriate for a non-EU Member State, but not for a member of the EU. ‘We are dissatisfied with the bank and the agreement’, Èiukšys says bluntly. ‘It is insufficient in financial terms. And the EBRD waters down responsibility. It shows no responsibility.’

The EBRD is reluctant to say much about the conflict. The London-based bank manages the International Ignalina Decommissioning Support Fund (IIDSF), which is financed by the EBRD, the EU and 15 donor countries. IIDSF has funded the construction of a 450 Megawatt gas-fired power plant in Lithuania and is paying for two decommissioning projects in Ignalina: the construction of a spent fuel storage facility and a radioactive waste treatment facility. In comments to EER, the EBRD said that the two decommissioning projects ‘have experienced problems for a variety of reasons, some technical, most commercial in nature’. It also said that ‘Ignalina’s new management, mostly recruited from outside the nuclear sector, has decided to deal with the issues at hand on their own without involving the bank’. This apparently refers to the change in the administration of the project after the new Lithuanian government took things in hand.

Own show

Ignalina nuclear power plant, Lithuania (photo: Jan Haverkamp)

For Èiukšys the solution is clear: ‘Leave management of the IIDSF to us. We know best how the money can be used most effectively.’ And he has the support of the Minister of Energy Sekmokas: ‘We want to manage the plant ourselves’, Sekmokas says. EBRD does not want to respond to this demand, except for saying that ‘the bank is very concerned and the resolution of the difficulties is taking much longer than was anticipated’.

Independent experts in Lithuania are critical of the government’s position. Professor Jurgis Vilemas, who was the Director of the Lithuanian Energy Institute until 2004, Chairman of the Institute’s Scientific Council until 2010 and Chief Researcher until very recently (23 August), said to EER: ‘Before the EU-accession in 2004, Lithuania listened and followed the advice it got. After the accession the strategy is: We run our own show.’

Vilemas says that in the Ignalina project ‘all professionals were replaced by people from the outside; they talk about mismanagement to cover up their intention to fire people from earlier times’. According to Vilemas, the EBRD should keep control of the project. ‘The party that is providing the funds should - and must - also be in control’.

Drop tests

The conflict with the EBRD is not the only battle Osvaldas Èiukšys is fighting. He also has a quarrel with GNS (Gesellschaft für Nuklear Service), the German company that is responsible for transporting the radioactive material from the water tanks at Ignalina and storing it at the spent fuel storage facility. This facility is located just a few hundred metres away from the plant and currently being built. GNS, specialised in radioactive waste disposal, is a joint-venture of the four major German energy companies Eon, RWE, ENBW and Vattenfall.

Ignalina’s management is critical of the quality of the casks that are meant to be used for the transport and storage of the radioactive waste. The Lithuanians claim that the casks have not been sufficiently tested and they want drop tests to be carried out. Èiukšys says the casks are ‘rubbish and dangerous’.

GNS, however, does not see any safety flaws. In a statement to EER the company declared that the

'The bank is very concerned and the resolution of the difficulties is taking much longer than was anticipated'
weight of the casks had been increased from 84.5 to 120 tonnes and that ‘they have been tested in a complete series of half-scale drop tests and without shock absorbers. Moreover, in 2004 a comparable tank underwent full-scale drop testing.’ In addition, during the design phase, a number of drop tests were carried out, so ‘any further drop tests would not result in additional safety or bring about new insights’.

The conflict means that the fuel rods of the first Ignalina reactor, which should have been moved to the storage facility, are still awaiting transport. As long as the pools of Ignalina 1 have not been emptied, reactor 2 cannot be unloaded either. This is further delaying the decommissioning process. According to Professor Vilemas, ‘both sides are responsible for the delay: mistakes have been made by everyone involved.’

No legacy

By now construction on the spent fuel storage facility is three to four years behind schedule. The hope is that it can go into operation in 2012. The government continues to cling to its ‘immediate dismantling’ strategy. In its mind, the entire plant should be dismantled without delay. It wants to make use of the existing workforce and operational infrastructure. This will be the least costly option and ‘leave no legacy for future generations’.

The latter is not entirely accurate. The spent fuel storage facility on the premises is planned to remain operational for 50 years. What will happen to the radioactive waste after that is still unclear. The original

'Before the EU-accession in 2004, Lithuania listened and followed the advice it got. After the accession the strategy is: We run our own show'
idea to send it back to Russia is no longer an option after the break-up of the Soviet Union. Two additional storage facilities – one for the disposal of short-lived, very low-level solid waste and a near-surface repository for short-lived low and intermediate-level radioactive waste – are planned that are supposed to provide reliable protection for 300 years.

If by 2029 all that remains of Ignalina is a ‘brown field’, the decommissioning of the first RBMK reactor will have cost €2.9 billion, based on today’s calculations. This is about as much as the cost of a new nuclear power plant. At the end of this year some €700 million will have been spent. Of the remaining €2.2 billion, some €1.5 billion has not yet been secured. The money is not likely to be forthcoming unless the government in Vilnius, the EU and the EBRD find common ground.

 

Visaginas to be built by Hitachi-GE … perhaps

On 14 July Hitachi-GE Nuclear Energy was selected as the “Strategic Investor” for the Visaginas Nuclear Power Plant Project planned by the Republic of Lithuania. The Japanese-US combination beat the US Westinghouse Electric Company which had also been in the race. ‘Strategic investor’ means that the company has ‘preferential negotiating rights for investment on the project, concession agreement and other contracts including the EPC [engineering, procurement and construction] contract’, according to the press release from GE-Hitachi. In other words, GE-Hitachi has not yet committed any money nor has a definite contract been signed.

In addition to Lithuania, the countries of Estonia, Latvia and Poland have announced their interest in the venture. But long-standing questions with regard to the feasability of the project have not been resolved. The most important question is whether Lithuania and the region really need a new nuclear power plant. Minister of Energy Arvydas Sekmokas thinks so. He says that the Baltic states and Poland simply cannot do without a new nuclear power plant.

The previous head of the Lithuanian Energy Institute, Jurgis Vilemas, who until very recently was its Chief Research Officer, disagrees. ‘Energy independence from Russia - definitely. A new nuclear power plant - definitely not.’ He says that a new power plant would not be profitable. In his opinion, Lithuania should rely on new interconnectors (with Sweden, Poland and Estonia/Finland) and on developing its own energy resources.

The EU’s Baltic Energy Market Interconnection Plan (BEMIP) was started up at the end of 2008 to integrate the Baltic region’s energy market with that of the EU by expanding electricity and gas interconnections. But this plan remains far from completed. Meanwhile, after Ignalina was shut down, electricity rates in Lithuania skyrocketed. The government claims they are the highest in Europe now. The first five months of this year alone they were 11.8% higher than in the same period in the previous year, when close to 70% of Lithuania's energy demands were still met by Ignalina.

The big question is who in the end will invest in the project. Lithuania’s neighbouring countries have not committed themselves yet. The Poles have plans to build their own reactors, and they are also keen on developing their shale gas deposits. Incidentally, the word in Lithuania now is that there may also be significant shale gas deposits in that country.

It does seem clear that despite being called a ‘strategic investor’, Hitachi GE will not use its own capital resources to become a nuclear power plant operator. The Lithuanian government has said it hopes to award the definitive construction contract for Visaginas at the end of this year.

 

More information

For earlier stories in European Energy Review on the Baltic energy market, see:

Russia proposes 'electricity pipeline' to Germany
'There is a total lack of competition in the regional gas market'
Lithuania trades in Ignaline for BaltPool
Baltic Region needs cooperation, not nationalism
Energy fever in the Baltics
Lithuania's nuclear power dreams
Baltic states torn between two lovers

For more information on the Baltic Energy Market Interconnection Plan (BEMIP), see the following pages on the website of the European Commission:
http://ec.europa.eu/energy/infrastructure/bemip_en.htm  
http://ec.europa.eu/energy/infrastructure/events/2009_11_25_bemip_conference_en.htm